Construction updated May 29, 2019
Construction schedule: - Completed concrete structure - Brick work, finishing work for buildings is up to 4th floor, civil work and landscape works are on going, Construction updated May 29, 2019
Construction updated March 23, 2020
Construction schedule: - Installing rebar and form work for technical roof slab of buildings - Brick work, finishing work for buildings is up to 4th floor, civil work and landscape works are on going , Construction updated March 23, 2020
Construction updated February 28, 2020
Construction schedule: - Installing rebar and form work for technical roof slab of buildings - Brick work, finishing work for buildings is up to 3rd floor, civil work are on going, Construction updated February 28, 2020.
ANNOUNCEMENT OF ADMINISTRATIVE STAFF
VKIST is now announcing the recruitment of administrative staffs, we are looking for experienced and administrative staffs who possess the skill and high spirit to build VKIST. They will play an important role making new paradigm of VKIST with global
Construction updated January 10, 2020
Construction schedule: - Installing rebar and form work for technical roof slab of buildings - Brick work, finishing work for buildings is up to 3rd floor, civil work are on going, Construction updated January 10, 2020
The 1st recruitment announcement for researcher in 2020
VKIST continues to announce recruitment of engineers for the Research area in Information Technology. We are seeking engineers with creativity and enthusiasm to make a breakthrough for national competition in the field of science and technology,
Construction updated November 12, 2019
Installing rebar and formwork of 4th floor column and 5th floor slab of MB, RB1. Installing rebar and formwork of technical roof slab of RB2. Installing rebar and formwork of roof slab of RB3.