
1109/2019
Construction updated September 10, 2019
Installing rebar and formwork of remaining 3rd floor slab and 4th floor slab of MB, RB1. Completed casting concrete 4th floor slab, Installing rebar and formwork of roof slab of RB2. Installing rebar and formwork of 4th floor slab of RB3.

2008/2019
Weekly construction updated August 20, 2019
Almost completed casting concrete of 3rd floor slab of MB, RB1. Installing rebar and formwork of 4th floor slab & roof slab of RB2. Installing rebar and formwork of 4th floor slab of RB3. , Weekly construction updated August 20, 2019

1208/2019
Weekly construction updated August 5, 2019
Installing rebar and formwork of 2nd floor column, 3rd floor slab of MB, RB1. Installing rebar and formwork of 4th floor slab of RB2. Installing rebar and formwork of 3rd floor column, 4th floor slab of RB3. , Weekly construction updated August 5, 2019

1008/2019
3RD RECRUITMENT ANNOUNCEMENT OF ADMINISTRATIVE STAFF
VKIST is now announcing the recruitment of administrative staffs, we are looking for experienced and administrative staffs who possess the skill and high spirit to build VKIST. They will play an important role making new paradigm of VKIST with global

0208/2019
RECRUITMENT ANNOUNCEMENT FOR THE MID-TIER RESEARCHER AND RESEARCHER
VKIST announces recruitment for the Mid-tier Researcher and Researcher. We are looking for researchers with creativity and enthusiasm to make a breakthrough for national competition in the field of IT and BT, contribute to build a new model for VKIST

0207/2019
RECRUITMENT ANNOUNCEMENT FOR P.I
Vietnam - Korea Institute of Science and Technology (VKIST) was established with the support of the Korean Government and is a Public Agency on Science and Technology under the Ministry of Science and Technology (MOST). The mission of VKIST is to lead

2406/2019
Weekly construction updated June 24, 2019
Installing rebar and formwork of a half remaining 2nd floor slab of MB, RB 1. Installing rebar and formwork of 1/3 remaining 2nd floor slab of RB 3. Installing rebar and formwork of 3rd floor slab of RB2 , Weekly construction updated June 24, 2019

2205/2019
Weekly construction updated May 21, 2019
Installing rebar and formwork of 1st floor wall and 2nd floor slab of MB. Installing rebar and formwork of 1st floor wall of RB1. Installing rebar and formwork of 2nd floor slab of RB2&3. Continues casting concrete Utility tunnel between buildings.

2304/2019
Weekly construction updated April 23, 2019
Main building and Research building 1 have completed 1st floor column concrete casting, continue to casting concrete 1st floor wall. Rebar and formwork for 2nd floor slab of Main building is being installed.

2204/2019
Weekly construction updated April 16, 2019
Columns of 1st floor, a part of wall of the 1st floor of Main building and Research building No.1 were completed. Concrete Foundation, Bracing, Reinforcing Steel of Research Building No.2 and No. 3 have been completed. Technical tunnels are being completed and partially poured.