Weekly construction updated June 24, 2019

Monday, 24/06/2019 | 15:14

Installing rebar and formwork of  a half remaining 2nd floor slab of MB, RB 1. Installing rebar and formwork of 1/3 remaining 2nd floor slab of  RB 3. Installing rebar and formwork of 3rd floor slab of RB2   , Weekly construction updated June 24, 2019

Installing rebar and formwork of a half remaining 2nd floor slab of MB, RB 1. Installing rebar and formwork of 1/3 remaining 2nd floor slab of RB 3. Installing rebar and formwork of 3rd floor slab of RB2

 

 