Installing rebar and formwork of 1st floor wall and 2nd floor slab of MB. Installing rebar and formwork of 1st floor wall of RB1. Installing rebar and formwork of 2nd floor slab of RB2&3. Continues casting concrete Utility tunnel between buildings.
Installing rebar of Machinery center 2's PIT floor wall. Completed lean concrete of waste water treatment center.
The exterior of main building and researcher buildings are basically completed. Tile, doors, plasterboard ceiling ...are being installed inside the building. The M&E technical system of the building is being installed synchronously all the floor.
Installing rebar and formwork of 4th floor column and 5th floor slab of MB, RB1. Installing rebar and formwork of technical roof slab of RB2. Installing rebar and formwork of roof slab of RB3.
The exterior of main building and researcher buildings are basically completed. Tile, doors, plasterboard ceiling ...are being installed inside the building. The M&E technical system of the building is being installed synchronously all the floor.