Columns of 1st floor, a part of wall of the 1st floor of Main building and Research building No.1 were completed. Concrete Foundation, Bracing, Reinforcing Steel of Research Building No.2 and No. 3 have been completed. Technical tunnels are being completed and partially poured.
The exterior of main building and researcher buildings are basically completed. Tile, doors, plasterboard ceiling ...are being installed inside the building. The M&E technical system of the building is being installed synchronously all the floor.
Installing rebar and formwork of 4th floor column and 5th floor slab of MB, RB1. Installing rebar and formwork of technical roof slab of RB2. Installing rebar and formwork of roof slab of RB3.
The exterior of main building and researcher buildings are basically completed. Tile, doors, plasterboard ceiling ...are being installed inside the building. The M&E technical system of the building is being installed synchronously all the floor.