Construction updated November 12, 2019
Installing rebar and formwork of 4th floor column and 5th floor slab of MB, RB1. Installing rebar and formwork of technical roof slab of RB2. Installing rebar and formwork of roof slab of RB3.
Construction update Oct 29, 2020
The exterior of main building and researcher buildings are basically completed. Tile, doors, plasterboard ceiling ...are being installed inside the building. The M&E technical system of the building is being installed synchronously all the floor.
Construction update Sept 29, 2020
The exterior of main building and researcher buildings are basically completed. Tile, doors, plasterboard ceiling ...are being installed inside the building. The M&E technical system of the building is being installed synchronously all the floor.
Construction update August 29, 2020
- The exterior of main building and researcher buildings are basically completed. - Tile, doors, plasterboard ceiling ...are being installed inside the building. - The M&E technical system of the building is being installed synchronously all the floor.
Construction update July 29, 2020
The exterior of main building and researcher buildings are basically completed. Tile, doors, plasterboard ceiling ...are being installed inside the building. The M&E technical system of the building is being installed synchronously all the floor.
The Recruitment Announcement (Researcher)
Pursuant to the Official Letter No. 296/BKHCN-TCCB of February 18, 2020 of the Ministry of Science and Technology on assigning the number of employees and labor contracts at the Vietnam-Korea Science and Technology Institute. VKIST announces the
Construction update June 29, 2020
The exterior of researcher 2 and 3 are basically completed, the exterior of the main house and the researcher 1 and the main building are expected to be completed in July.